How to run an ERP cutover rehearsal

A rehearsal exposes delays and unclear decisions before the live change.

What to do

  1. List the export, import, validation and integration steps in order with an owner for each.
  2. Time the rehearsal and test a transaction that crosses inventory, shipment and billing.
  3. Record the latest acceptable decision time and who can pause the cutover. Retest the slow or uncertain steps before launch.